A method for improving plant availability with respect to utilities using buffer tanks

Författare

  • Anna Lindholm

Summary, in English

Disturbances on utilities, such as steam and cooling water, often cause large revenue losses at industrial sites. These disturbances are often hard to handle, since they commonly are plant-wide disturbances that affect more than one production area at the site. Also, the production areas of the site are often dependent on other production areas because of the flow of product through the site, which makes the effect of disturbances on utilities hard to predict. In this paper, a simple method for decreasing the revenue loss due to disturbances on utilities is presented, where production areas are modeled as either operating at full speed or not operating (on/off), and buffer tanks between areas at the site are utilized. Both choice of levels in the buffer tank and control of the product flow at the site during a disturbance are discussed.

Publiceringsår

2011

Språk

Engelska

Publikation/Tidskrift/Serie

[Host publication title missing]

Dokumenttyp

Konferensbidrag

Ämne

  • Control Engineering

Nyckelord

  • Disturbance localization
  • availability
  • buffer tanks
  • plant-wide disturbances

Conference name

31st IASTED International Conference on Modelling, Identification, and Control (MIC)

Conference date

2011-02-16

Conference place

Innsbruck, Austria

Status

Published

Projekt

  • PICLU

Forskningsgrupp

  • LCCC